National Grid buys Dorman Point land for Teesside substation near planned AI datacentre
National Grid has agreed to buy 73 acres at Dorman Point on Teesside as a step towards building Britain's biggest electricity substation - a National Grid Teesside substation project on a Teesworks site that could power a neighbouring AI datacentre.
National Grid buys Dorman Point land for Teesside substation near planned AI datacentre
A 73-acre deal at Dorman Point
National Grid has agreed to purchase 73 acres of land at Dorman Point on Teesside, moving forward with plans for what would be the biggest electricity substation in Britain. The National Grid Teesside substation would sit on land owned by Teesworks, a local private-public partnership, and the deal was first reported by Sky News.
Key points of the deal:
- 73 acres at Dorman Point, Teesside, purchased by National Grid
- The site is owned by Teesworks
- Balfour Beatty was reported to be in line to deliver the substation, with Steel River Power (SRP) heavily involved
Power for a planned AI datacentre
The substation could supply power to a vast neighbouring datacentre. Last year, the UK government reportedly picked Teesworks as the site for a new artificial intelligence datacentre, and planning applications have since been submitted for a project of nearly 500,000 sq metres.
Ben Houchen, Tees Valley combined authority mayor, said: "Everyone who has tried to build a datacentre in this country knows the biggest problem is getting enough power to the site quickly."
What National Grid and the mayor said
Matt Pearce, head of land at National Grid, said the deal reflects the constructive work between all those involved to enable this vital infrastructure, supporting the growth of AI and digital technologies.
"We are committed to working closely with our partners to progress the development as quickly as possible," Pearce said.
Houchen added that having up to 3.2GW of capacity at the site would let Britain compete for datacentre projects that the US, Gulf and Europe have been winning. "I'd much rather that was Teesside than Texas or Abu Dhabi," he said, arguing Britain needs somewhere to physically put AI capability.
Policy backdrop and local opposition
The deal comes as the government published a draft national policy statement on datacentres last week, describing them as fundamental to the economy as the railways and electricity networks and saying the country must take control of their development.
Opposition to datacentre building is not confined to Teesside:
- Campaign groups have protested planned developments from Auchtertool, north of Edinburgh, to Brick Lane in east London
- In October, AI companies told ministers they had 12 months to head off public opposition to UK datacentres or risk US-style protests threatening construction
Balfour Beatty and SRP were approached for comment on the reported delivery role.