UK gigafactory project loses second builder as TSL exits Agratas site at Bridgwater
TSL has become the second construction contractor in five months to leave the UK's £5.2bn gigafactory project at Bridgwater, Somerset, after failing to agree terms with builder Agratas, the Tata Group company making Jaguar Land Rover batteries.
UK gigafactory project loses second builder as TSL exits Agratas site at Bridgwater
Why TSL is walking off the Bridgwater site
Construction specialist TSL, formally known as Tonroe Group, has decided to leave the £5.2bn uk gigafactory project after failing to agree terms with Agratas, according to three sources. The disagreement stemmed from disputes over the timeline and cost of the project, two sources said.
- TSL is expected to leave the site within two or three months.
- No other main build contractor is currently lined up.
- NG Bailey, the project's mechanical, electrical and plumbing contractor, is thought to be one option to take over the entire build.
A project that keeps slipping
Tata announced the gigafactory in 2023, aiming for a 2026 start of production with as many as 4,200 employees, before pushing it back to 2027. Agratas' latest target is a January 2028 start of production, and the company has not yet pushed back that planned start date despite the contractor dispute.
The UK government has pledged £380m in financial support for the factory, though not all of the subsidy has been paid out. On the ground, the shell of the Somerset building is mostly complete, and National Grid has started work on the electricity substation that will provide the large amounts of power needed to make batteries.
Sir Robert McAlpine and the morale problem
TSL's departure follows the exit of the previous contractor. Agratas fired Sir Robert McAlpine at short notice in June, and one source suggested discussions over the terms of its departure remain ongoing.
Internally, morale at Agratas has been hit by relocating some workers from Coventry to Somerset. Some of those workers are expected to take redundancy rather than uproot families and move 120 miles away. Two sources said such departures would continue a stream of senior staff leaving the business in recent months. Some Agratas managers have travelled to India this week to share experiences with counterparts at the company's battery site in Sanand, western India, and discuss the UK situation.
What it means for Jaguar Land Rover
JLR has secured batteries from other suppliers, so its plans to increase sales of new electric Land Rovers and Jaguars will not be affected, though those cars will not have British-made batteries. The manufacturer could also avoid EU tariffs under "rules of origin" if it uses batteries made in Europe.
The Somerset troubles come after AESC, whose Sunderland plant is the UK's only operating gigafactory, shelved expansion plans after it failed to agree a separate deal to supply JLR - a situation revealed in August. People close to the Agratas project believe it could still succeed, avoiding the fate of Britishvolt, which collapsed after failing to secure firm orders; the former Britishvolt site in north-east England is now being turned into a datacentre for artificial intelligence.
Agratas said: "We are on track to meet our customer requirements."
TSL and JLR declined to comment, while Agratas and NG Bailey were approached for comment.