How a $1.6bn Menomonie datacenter project was halted after secret NDAs surfaced
A secretive $1.6bn Menomonie datacenter - an AI hyperscale campus proposed just outside the Wisconsin city in spring 2025 - was halted after public opposition, following months in which two city officials signed NDAs with developer Balloonist LLC without telling the full council.
How a $1.6bn Menomonie datacenter project was halted after secret NDAs surfaced
Weeks into Sydney Brennan's term as a newly elected councilwoman in Menomonie, Wisconsin, consultants arrived pitching a $1.6bn AI hyperscale datacenter campus that an undisclosed big tech company wanted to build just outside town. The Menomonie datacenter story that followed is one of a small city facing the largest development in its history, largely behind closed doors.
A secret pitch behind closed doors
The planned 320-acre site would have used an estimated 75,000 gallons of water per day, and would have been the largest development in Menomonie's nearly 150-year history. The developer was Balloonist LLC, a shell company incorporated in Delaware; the identity of the parent corporation was known to only a few people, including two officials who had signed NDAs.
- The consultants projected up to 1,000 temporary construction jobs, along with hundreds of contractors and between 50 to 75 high-paying permanent jobs
- Balloonist's stated goal was to replenish more water than it consumed, by 2030
- In February 2024, city administrator Eric Atkinson and public works director David Schofield signed one-page NDAs with Balloonist that made no mention of a datacenter and instructed signatories they could not reveal the tech company or the agreement's existence
- A month after signing, Schofield proposed an ordinance defining 'warehousing' to include 'storage, management, processing, and transmission of digital data'; the council approved it in April 2024
The two sides worked in secret for nearly 18 months, until the city government put out a press release about the proposed project in July 2025. Atkinson, who attended the initial meeting, said the datacenter was just 'one of many ideas' to expand a local tech park. NDAs were reportedly signed in at least four other Wisconsin cities; officials in Beaver Dam also signed NDAs with Balloonist, whose $1bn project there was later revealed to be Meta.
The council learns about it late
In March 2025, councilmembers were only just learning of the project - more than a year after Atkinson and Schofield signed their NDAs. The city had already signed a pre-development agreement with Balloonist after the council approved it in closed session that March, a month before Brennan took office. That agreement allowed Balloonist to reimburse the city up to $200,000 to conduct site, environmental and traffic reviews.
Councilmember Cody Gentz recalled having little to go on. "I don't remember having any real information on it, other than you know this is a thing that we might look into," Gentz said. He described the mood in the closed-session room as "pretty neutral", with members seeing the project as potentially providing badly needed tax revenue.
Councilmember Chad Schlough admitted he had no 'frame of reference' for what a datacenter was and turned to an unusual source to prepare for his meeting with Balloonist's consultants. "I used CHATGPT: Discuss the pros and cons of allowing a datacenter into a small town," Schlough wrote to Atkinson. "CHATGPT is amazing." He believed the consultants were more interested in gauging how councilmembers would vote.
To move forward, Balloonist needed a council majority to approve annexation of land parcels it had targeted - which were not within city limits but in a neighboring village - and rezone them for industrial use. UW-Madison political science professor Barry Burden noted how much rests on such small bodies. "In terms of regulations and approvals, it's just a few volunteer town board members who are the main gatekeepers," he said.
Public opposition erupts
Tim Accola learned of the project in July 2025 when he returned home from a work trip to a surprise letter in his mailbox; his 1899 former schoolhouse and church home sits across the road from the proposed site. At the August council meeting, public comment ran for nearly two and a half hours, and Accola said he would be forced to sell his home if the project went ahead due to the excessive noise.
Despite the outcry, Brennan and a majority of her colleagues that night voted in favor of annexation and rezoning the land for industrial use. Organized resistance was building elsewhere: Blaine Halverson, one of the organizers behind the Stop the Menomonie Data Center Facebook group, which has nearly 11,000 members, said of the process that "It was like a black box to get any information".
Atkinson and Schofield did not respond to requests for comment, and an attorney for Balloonist LLC also did not respond.
How the project was paused
Mayor Randy Knaack responded to the groundswell of opposition and halted the project in a tersely worded memo. Looking back, he said the city - with a small staff and little expertise around datacenters - was "way in over their head" with Balloonist, and that NDAs should never have been signed for a project of that size.
"I felt like their attorneys were more in control of the process than we were," said Knaack. Wisconsin's tax incentives allowed Balloonist to apply for a sales tax exemption on any equipment used to build the datacenter; Knaack called the pitch 'slick' but was skeptical of the fine print.
In January, the council unanimously passed a zoning ordinance reversing the warehousing definition and creating a new datacenter zone. The move effectively paused, though it did not cancel, the development. Knaack, who had held the mayor's office for 16 years, lost his re-election this April.