Belgian authorities order Google to halt datacentre construction over lack of permits
WORLD · ENVIRONMENT

Belgian authorities order Google to halt datacentre construction over lack of permits

Belgian authorities have ordered Google to stop work on a large datacentre at Aiseau-Presles in southern Belgium after its requests to modify the original planning permission went unapproved, with inspectors finding the building nearly complete.

By LiveDigestPublished Friday, November 27, 2026 · 18:42 GMT | 2 min read

Belgian authorities order Google to halt datacentre construction over lack of permits

Inspectors who visited the site of Google's datacentre in Belgium found the structure was all but finished, its structural work done, even though the permit covering it had been refused, regional official Raphaël Stokis told RTBF.

As a result, authorities issued a wallonia stop-work order: the 300 workers on site received a verbal instruction to stop, which was later confirmed in writing to Google.

01 / ENVIRONMENT

How the permit unraveled

The dispute traces back to what Google was originally allowed to build. Its 2024 permit covered three smaller datacentres cooled by air. In 2025 the company applied to merge two of them into a single larger building with liquid cooling, drawing 600 cubic metres of water an hour from the nearby Sambre River.

  • The regional administration approved the amendments in April 2025, but residents and protest groups appealed.
  • In August, Wallonia infrastructure minister François Desquesnes revoked the modified permit, citing drought concerns.
02 / ENVIRONMENT

Protesters, prosecutors and next steps

Greenpeace published a report with greenpeace drone footage showing Google was still carrying on construction at the site, even after the latest version of its planning permission was revoked in August. The group also said it had filed an emergency appeal with local planning authorities.

Meanwhile, regional government spokesperson Nicolas Yernaux told AFP on Friday that a report was being submitted to public prosecutors alleging the illegal construction permit breach - the building of a 3-hectare facility described as a major offence.

Google said in a statement it was:

committed to maintaining an open and collaborative dialogue

The company has appealed the revocation to Belgium's council of state, where a ruling in the case is expected on 7 January.

03 / ENVIRONMENT

Site and wider picture

The building stands on about 3 hectares (7.4 acres) within a 50-hectare business park on a former coalmine site at Aiseau-Presles, roughly 15km west of Charleroi. It was one of three datacentres Google originally planned for the location.

The project is not the only one of Google's European plans under scrutiny: in October, Finland opened a criminal investigation into possible breaches of environmental law at a planned Google datacentre in rural northern Finland, where work is halted until environmental impact assessments are completed.

Belgian authorities order Google to halt datacentre construction over lack of permits
WORLD · ENVIRONMENT

Belgian authorities order Google to halt datacentre construction over lack of permits

Belgian authorities have ordered Google to stop work on a large datacentre at Aiseau-Presles in southern Belgium after its requests to modify the original planning permission went unapproved, with inspectors finding the building nearly complete.

By LiveDigestPublished Friday, November 27, 2026 · 18:42 GMT | 2 min read

Belgian authorities order Google to halt datacentre construction over lack of permits

Inspectors who visited the site of Google's datacentre in Belgium found the structure was all but finished, its structural work done, even though the permit covering it had been refused, regional official Raphaël Stokis told RTBF.

As a result, authorities issued a wallonia stop-work order: the 300 workers on site received a verbal instruction to stop, which was later confirmed in writing to Google.

01 / ENVIRONMENT

How the permit unraveled

The dispute traces back to what Google was originally allowed to build. Its 2024 permit covered three smaller datacentres cooled by air. In 2025 the company applied to merge two of them into a single larger building with liquid cooling, drawing 600 cubic metres of water an hour from the nearby Sambre River.

  • The regional administration approved the amendments in April 2025, but residents and protest groups appealed.
  • In August, Wallonia infrastructure minister François Desquesnes revoked the modified permit, citing drought concerns.
02 / ENVIRONMENT

Protesters, prosecutors and next steps

Greenpeace published a report with greenpeace drone footage showing Google was still carrying on construction at the site, even after the latest version of its planning permission was revoked in August. The group also said it had filed an emergency appeal with local planning authorities.

Meanwhile, regional government spokesperson Nicolas Yernaux told AFP on Friday that a report was being submitted to public prosecutors alleging the illegal construction permit breach - the building of a 3-hectare facility described as a major offence.

Google said in a statement it was:

The company has appealed the revocation to Belgium's council of state, where a ruling in the case is expected on 7 January.

committed to maintaining an open and collaborative dialogue
03 / ENVIRONMENT

Site and wider picture

The building stands on about 3 hectares (7.4 acres) within a 50-hectare business park on a former coalmine site at Aiseau-Presles, roughly 15km west of Charleroi. It was one of three datacentres Google originally planned for the location.

The project is not the only one of Google's European plans under scrutiny: in October, Finland opened a criminal investigation into possible breaches of environmental law at a planned Google datacentre in rural northern Finland, where work is halted until environmental impact assessments are completed.

Belgian authorities order Google to halt datacentre construction over lack of permits
WORLD · ENVIRONMENT

Belgian authorities order Google to halt datacentre construction over lack of permits

By LiveDigest

Belgian authorities order Google to halt datacentre construction over lack of permits

Inspectors who visited the site of Google's datacentre in Belgium found the structure was all but finished, its structural work done, even though the permit covering it had been refused, regional official Raphaël Stokis told RTBF.

As a result, authorities issued a wallonia stop-work order: the 300 workers on site received a verbal instruction to stop, which was later confirmed in writing to Google.

01 / ENVIRONMENT

How the permit unraveled

The dispute traces back to what Google was originally allowed to build. Its 2024 permit covered three smaller datacentres cooled by air. In 2025 the company applied to merge two of them into a single larger building with liquid cooling, drawing 600 cubic metres of water an hour from the nearby Sambre River.

  • The regional administration approved the amendments in April 2025, but residents and protest groups appealed.
  • In August, Wallonia infrastructure minister François Desquesnes revoked the modified permit, citing drought concerns.
02 / ENVIRONMENT

Protesters, prosecutors and next steps

Greenpeace published a report with greenpeace drone footage showing Google was still carrying on construction at the site, even after the latest version of its planning permission was revoked in August. The group also said it had filed an emergency appeal with local planning authorities.

Meanwhile, regional government spokesperson Nicolas Yernaux told AFP on Friday that a report was being submitted to public prosecutors alleging the illegal construction permit breach - the building of a 3-hectare facility described as a major offence.

Google said in a statement it was:

The company has appealed the revocation to Belgium's council of state, where a ruling in the case is expected on 7 January.

committed to maintaining an open and collaborative dialogue
03 / ENVIRONMENT

Site and wider picture

The building stands on about 3 hectares (7.4 acres) within a 50-hectare business park on a former coalmine site at Aiseau-Presles, roughly 15km west of Charleroi. It was one of three datacentres Google originally planned for the location.

The project is not the only one of Google's European plans under scrutiny: in October, Finland opened a criminal investigation into possible breaches of environmental law at a planned Google datacentre in rural northern Finland, where work is halted until environmental impact assessments are completed.